2026 Road Program Tentative Schedule
- August 17th – September 30th, 2026: ADA Ramps throughout Tower Hill Grove Development (Cipolloni Concrete) – COMPLETED
- September 21st – October 31st, 2026: Milling and Paving (JDM Paving)
ADA Ramps (concrete work) – COMPLETED
- Tower Hill Grove Development (Blackburn Dr., Grove Circle, Nightengale Circle, Blossom Hill Lane, Morningside Circle, Belle View Way)
Milling and Paving – Tentatively Beginning Monday, September 21st, 2026
- Tower Hill Grove Development (Blackburn Dr., Grove Circle, Nightengale Circle, Blossom Hill Lane, Morningside Circle, Belle View Way)
- JDM Paving is tentatively scheduled to begin paving in the Blackburn Development on Monday, September 21st.
- Once the Tower Hill Grove Development is completed, JDM Paving will move to the Oxbow Ridge Development.
- Oxbow Ridge Development (Cassandra Drive, Shady Hill Drive, Thornburry Court)